Camden Bridges Update

The recent floods have significantly impacted a number of Camden’s Bridges. Works are underway to investigate the scale of damage, undertake repair works and reopen these assets to the community.

The damage caused is generally due to riverbank erosion or the collapsing of the riverbank adjacent to our bridge structures. There are various possible contributing factors as flood events over the past couple of years have seen the bridges repeatedly inundated.

This page aims to provide a summary of progress as relevant information is made available to Council.

We are working hard to reopen the bridges as quickly and safely as possible. We appreciate your patience.

Cobbitty Bridge

Cobbitty Bridge is located on the boundary between Wollondilly and Camden Local Government Areas.

Maintenance of the bridge structure is managed by Wollondilly Shire Council.

The roads on the approach to the bridge and the bridge have been closed since damage occurred following the July 2022 flood event, the largest flood of the past four events.

A large area of embankment on the Camden side of the bridge was part of a landslip into the river resulting in a large area of road collapsing.

Camden Council is working with specialist consultants to conduct investigations and design a suitable repair solution. It is difficult to estimate timing for expected repair works until more information is known.

Council will provide an update when more information is available.

Update 10 August 2022

  • Consultants SMEC have been engaged to look at options for Cobbitty Bridge , undertake investigations and prepare concept designs
  • Preliminary concept options are now complete and a preferred options has been selected.
  • Design development of the preferred option is expected to be completed by the end of August. This will then provide a timeframe for construction.
  • Geotech testing is scheduled for Wednesday 10 August 2022.

293965392 415710713933670 1737895700497256870 n

Macquarie Grove Bridge

Macquarie Grove Bridge has been affected by recent floods. It was originally damaged in the March 2022 flood when the riverbank on the Camden side of the bridge collapsed.

Camden Council has been working with specialist consultants to investigate and design suitable options to repair the bridge.

Estimated timeframes are yet to be established until more information is known following the latest flood event. Council will keep the community updated as information becomes available.

Update 10 August 2022

  • Survey monitoring is ongoing.
  • Survey and Geotech assessment has been completed.
  • Site inspections by Structural Engineer and Water Resources Engineer completed. 
  • Concept design option are in progress and are expected to be completed by the end of August 2022. 

Update 22 July 2022

  • Camden Council has reopened Macquarie Grove bridge under single lane traffic arrangements.
  • Regular survey monitoring will be carried out.

293463851 415710703933671 1449073579317763169 n

Little Sandy Bridge

Little Sandy Bridge is a pedestrian bridge located between the Nepean Cycleway at Chellaston Street, Camden and River Road Reserve, Elderslie.

Damage to the riverbank on the Elderslie side of the bridge has been worsening with each flooding event.

Camden Council has been working with specialist consultants to investigate and design suitable options to repair Little Sandy Bridge including possible improvements.

Estimate timeframes for repair works are unable to be provided until more information is known following the latest flood event. Council will keep the community updated as information becomes available.

Update 10 August 2022

  • Survey works have been engaged and are in progress.
  • Design consultants have been engaged.
  • Concept design options are in progress and expected to be completed by mid September 2022. 

Little Sandy Bridge 3 by Jai Cooper