Little Sandy Bridge
Little Sandy Bridge is a pedestrian bridge located between the Nepean Cycleway at Chellaston Street, Camden and River Road Reserve, Elderslie.
Significant damage to the bridge approach and riverbank on the eastern side occurred during four flood events in 2022.
Council recently accepted a tender for the rectification works to Little Sandy Bridge.
Works are expected to commence in May and be completed by the end of 2025, weather permitting.
Project Updates
Updated 8 November 2022 Updated 14 October 2022 Updated 5 September 2022 Updated 10 August 2022 Updated 3 November 2023 Council has confirmed the preferred rectification option. Quotations are being sought from specialist design consultants to undertake the detailed design. Design is scheduled to commence in December. Once design proposals are received and a contract is awarded the scheduled commencement date for construction will be confirmed. Updated 18 September 2023 A peer review of the concept design options for rectification of the damage to Little Sandy Bridge has been completed. Concept designs will now be completed and presented to Council in October for approval to proceed with the preferred option; Following adoption of the preferred option, Council will proceed to engage a consultant for detail design. Updates will be provided regarding timeframes expected to complete the detail design and issue a tender for construction. Updated 13 June 2023 Council has completed concept design options for the rectification of the damage to Little Sandy Bridge. A peer review of the options is being undertaken before detail design commences. Further updates on timing will be provided once detailed design commences. Updated 21 March 2023 Additional survey works and flood modelling, required due to the significant changes to the river banks have been completed. This information has been used to inform a review of and modification to the concept design options. Final design options and cost estimates are now completed and are being considered by Council. Once a preferred concept is agreed, consultants will be contracted to undertake the detailed design. Further updates on timing will be provided once detailed design commences. Updated December 2024 Updated April 2025 Updated February 2025
2022
2023
2024
2025
Frequently Asked Questions (FAQs)
Little Sandy Bridge is a pedestrian bridge located over the Nepean River linking Camden and Elderslie via the Nepean Cycleway at Chellaston Street and River Road Reserve. The bridge was temporarily closed in March 2022 due to the abutment (the substructure at the end of the bridge that joins the bridge to land) being undermined as well as damage to the pathway approaching the bridge. More recent floods in March and June 2024 resulted in further damage to the eastern (Elderslie) side of the bridge, washing away the bridge approach, pathway and large sections of the riverbank and vegetation. The flooding events resulted in significant damage to the riverbank, impacting access to the bridge including: The area of rectification work required is approximately 2,750m2 and will require approximately 8,500 tonne of rock fill and rock scour protection to be installed. Little Sandy Bridge - February 2022 Little Sandy Bridge - August 2022 Little Sandy Bridge - June 2024 The following works will be undertaken prior to reopening Little Sandy Bridge: Council has been working extensively with industry experts to help ensure the rectification works will withstand future flooding events. While no works can be guaranteed not to be impacted by flooding events to some degree, we are confident the surveying and modelling works, as well as undertaking a peer review of the concept design, will provide the best rectification option available. Following the construction of the pre-cast concrete bridge in April 2014, Little Sandy Bridge has been subjected to many flooding events. Whilst the bridge itself has withstood the floods, the bridge approach on the eastern (Elderslie side) has suffered considerable damage. If Council were able to undertake rectification works following the first flooding event, it is likely Council would still be undertaking works to a similar scale. The quantity and speed of flood waters the Nepean River experienced in the floods in March and June 2024 caused significant damage. With the flooding events so close together, the riverbank wasn’t able to recover or naturally restabilise between each flood resulting in significant erosion. Council recently awarded a contract for the rectification works to Menai Civil Contractors. Works will commence in May 2025 and are expected to be completed by the end of 2025, weather permitting. The $3.7 million project rectification works are partially funded by the Australian and the Department of Regional NSW.
Where is Little Sandy Bridge?
Why was Little Sandy Bridge closed?
What damage has occurred?
What repairs are required to reopen Little Sandy Bridge?
Will these works withstand future floods?
Weren’t the repairs to the Bridge in 2014 meant to make it ‘flood-proof’?
Would the works have been as extensive if repair works had been completed after the first flooding event?
Where is the project up to?
How is the project funded?