Oran Park Leisure Centre

Oran Park2

Project name: Oran Park Leisure Centre

Project address: 74 Central Avenue, Oran Park

Ward: North

Project outcome: 

The Oran Park Leisure Centre will be a significant addition to the precinct. Incorporating aquatic, indoor sports, health and fitness areas, it will be a multipurpose community facility, offering a large variety of activities and services for all age groups. It will be a place for social gathering, providing unification between the existing Library and Camden Council administration building. 

Project budget: $63.3M. 

This project is co-funded by Camden Council and Greenfields Development Company. 

Expected completion date: September 2024

In February 2021, Councillors approved the concept Design for the new Leisure Centre.

Project Timeline:

  • June 2020: Warren & Mahoney engaged as the Head Consultant for the project.
  • November 2020: Concept design completed.
  • February 2021: Schematic design completed.
  • June 2021: DA lodged for assessment.
  • November 2021: DA approved.
  • December 2021: EOI for contractor. Detailed design completed.
  • December 2021: DA determination received.
  • March 2022: Early works commencing. 
  • July 2022: Early works completed.
  • August 2022: ADCO Construction engaged as the main contractor for the project.
  • September 2022: Works start on site. 
  • November 2022: Inground and Pilling works completed to the pools. 
  • January 2023: Concrete structure to the 50m pool completed. 
  • February 2023: Basement carpark first pour completed. Ground floor formwork commencing. 
  • March 2023: Leisure and Learn to Swim pool shell structures commenced. Basement carpark concrete pours continuing. 
  • April 2023: Leisure and Learn to Swim Pool structure complete. Basement carpark completed.
  • May 2023: Concrete structure to gym and courts complete. Pool inground plumbing completed. Pool water tests completed.
  • June 2023: Carpark painting and electrical works. Pool filters installed. Roof plantroom concrete structure.
  • July 2023: Completion of concrete works. Delivery of long lead equipment and fittings.
  • August 2023: Installation of the glulam timber beams to the 50m pool hall. Removal of formwork. Blockwork walls commence.
  • September 2023: Installation of glulam timber beams to the Learn to Swim pool hall. Structural steel installation to the 50m pool hall. Change room walls installed. Major air conditioning equipment lifted in place to the roof. Pool equipment installation.

Progress Photos:

September 2023

DJI 0026x2DJI 0025x2

August 2023:

DJI 0343 copyDJI 0335 copy

June 2023:

 DJI 0033 Oran Park Leisure Centre 19062023DJI 0032 Oran Park Leisure Centre 19062023DJI 0031 Oran Park Leisure Centre 19062023

March 2023:

DJI 0040

DJI 0041

February 2023:

TYGK8921

NDSA4910