Oran Park Leisure Centre

Oran Park2

Project name: Oran Park Leisure Centre

Project address: 74 Central Avenue, Oran Park

Ward: North

Project outcome: 

The Oran Park Leisure Centre will be a significant addition to the precinct. Incorporating aquatic, indoor sports, health and fitness areas, it will be a multipurpose community facility, offering a large variety of activities and services for all age groups. It will be a place for social gathering, providing unification between the existing Library and Camden Council administration building. 

Project budget: $63.3M. 

This project is co-funded by Camden Council and Greenfields Development Company. 

Expected completion date: September 2024

In February 2021, Councillors approved the concept Design for the new Leisure Centre.

Project Timeline:

  • June 2020: Warren & Mahoney engaged as the Head Consultant for the project.
  • November 2020: Concept design completed.
  • February 2021: Schematic design completed.
  • June 2021: DA lodged for assessment.
  • November 2021: DA approved.
  • December 2021: EOI for contractor. Detailed design completed.
  • December 2021: DA determination received.
  • March 2022: Early works commencing. 
  • July 2022: Early works completed.
  • August 2022: ADCO Construction engaged as the main contractor for the project.
  • September 2022: Works start on site. 
  • November 2022: Inground and Pilling works completed to the pools. 
  • January 2023: Concrete structure to the 50m pool completed. 
  • February 2023: Basement carpark first pour completed. Ground floor formwork commencing. 
  • March 2023: Leisure and Learn to Swim pool shell structures commenced. Basement carpark concrete pours continuing. 
  • April 2023: Leisure and Learn to Swim Pool structure complete. Basement carpark completed.
  • May 2023: Concrete structure to gym and courts complete. Pool inground plumbing completed. Pool water tests completed.
  • June 2023: Carpark painting and electrical works. Pool filters installed. Roof plantroom concrete structure.
  • July 2023: Completion of concrete works. Delivery of long lead equipment and fittings.
  • August 2023: Installation of the glulam timber beams to the 50m pool hall. Removal of formwork. Blockwork walls commence.

Progress Photos:

August 2023:

DJI 0343 copyDJI 0335 copy

June 2023:

 DJI 0033 Oran Park Leisure Centre 19062023DJI 0032 Oran Park Leisure Centre 19062023DJI 0031 Oran Park Leisure Centre 19062023

March 2023:

DJI 0040

DJI 0041

February 2023:

TYGK8921

NDSA4910